EOT Claims in UAE Construction: Extension of Time, FIDIC Notices and Delay Compensation

Mr. Mohamed Ghanem

Published

Updated

Your project is late because drawings were delayed, access was restricted or the employer instructed additional work. Can you extend the completion date, avoid delay damages and recover additional costs? An Extension of Time (EOT) claim may provide a remedy, but it is not automatic. The contractor must identify a qualifying contractual event, comply with the applicable claims procedure and prove its effect on completion.

Many UAE projects use amended FIDIC standard forms. The executed General and Particular Conditions—not an online summary—determine the applicable notice periods and entitlements. The legal analysis must also consider the UAE's current Civil Transactions Law, Federal Decree-Law No. 25 of 2025, which came into force on 1 June 2026, subject to applicable transitional questions.

1. What is an Extension of Time?

An EOT adjusts the contractual date for completion or a specified milestone where the relevant contract permits an extension. It may reduce exposure to delay damages for the properly extended period. Additional time and additional money are different entitlements. A delay may justify an EOT without entitling the contractor to prolongation costs.

Simple example

If the contract completion date is 30 June and a qualifying critical delay justifies 30 days, the revised date may become 30 July, assuming the contract's rules and assessment support the full extension. A delay to a non-critical activity may not change completion at all.

2. Which events may justify an EOT?

Depending on the contract and allocation of risk, potential events include:

  • Employer-caused late access or possession.
  • Late drawings, instructions or approvals.
  • Employer variations affecting critical work.
  • Delays caused by separately appointed contractors.
  • Exceptionally adverse climatic conditions, where recognised.
  • Qualifying exceptional events or force majeure-type circumstances.
  • Certain authority or utility delays, where risk is not allocated to the contractor.

The event's label is not enough: the contractor must show contractual entitlement, causation and actual impact on completion.

EventEOT possible?Prolongation costs possible?
Employer delays critical drawingsPotentiallyPotentially
Employer variation affecting critical pathPotentiallyPotentially
Exceptional weatherContract-dependentOften restricted
Contractor's own labour shortageUsually notUsually not
Qualifying exceptional eventContract-dependentSeparately assessed

3. FIDIC notices and time bars

Is a 28-day notice always required?

No. The often-cited 28-day requirement is contractual, not a universal UAE statutory deadline. In the unamended FIDIC Red Book 1999, Sub-Clause 20.1 includes a claims notice mechanism; the 2017 edition uses a revised claims procedure in Sub-Clause 20.2. The 1999 and 2017 editions differ in important respects, and Particular Conditions may change either.

When does time start running?

The contract may trigger the notice period when the contractor became aware, or should have become aware, of the event or circumstance. Waiting until the full delay has been quantified can be risky. Check the precise trigger, recipient, method of service and subsequent detailed-claim deadlines.

What should a notice say?

Identify the contract, event, dates, relevant clause, affected works, anticipated impact and claimed relief. Keep evidence of delivery. A routine site email may not satisfy a formal notice clause.

What happens after late notice?

A late notice may create serious entitlement risks. Its effect depends on the contract edition, amendments, procedural responses, governing law and facts. Do not assume every late claim is automatically barred—or automatically excused.

4. How to prepare a credible EOT claim

Step 1: Review the contract

Identify the EOT clause, claims procedure, programme duties, variations provisions, risk allocation and dispute resolution requirements.

Step 2: Preserve the baseline and updated programmes

Retain the accepted baseline, logic links, milestones and contemporaneous updates. An EOT analysis should assess the programme as the project actually developed, not merely compare two completion dates.

Step 3: Collect contemporaneous records

Keep site diaries, daily reports, photographs, instructions, drawing logs, inspection requests, labour and plant records, meeting minutes, authority correspondence and payment records.

Step 4: Demonstrate causation

Show how the qualifying event affected a critical or otherwise completion-driving activity. For example, late structural drawings may delay reinforcement, which delays concrete placement and subsequent critical work. Merely proving drawings were late does not establish the number of EOT days.

Step 5: Quantify the extension

Use an appropriate delay analysis and explain assumptions, data quality and the impact of any concurrent events.

Step 6: Separate time and cost submissions

Set out the EOT days and any prolongation claim as distinct requests, each supported by the required contractual basis and evidence.

5. Critical path, concurrency and prolongation costs

What is critical path analysis?

The critical path is the sequence of activities determining completion under the relevant programme. A delayed activity with sufficient float may not affect the completion date. Programme logic, updates and actual progress matter.

Which delay analysis method should be used?

Common approaches include time impact analysis, windows analysis, as-planned versus as-built, impacted as-planned and collapsed as-built. The Society of Construction Law Delay and Disruption Protocol, Second Edition provides widely used professional guidance on methodology, contemporaneous records and delay assessment. The Protocol is not UAE legislation and does not override the contract.

What is concurrent delay?

Concurrent delay involves overlapping events attributable to different parties that are each causally effective in delaying completion. Two problems occurring in the same calendar month are not necessarily concurrent critical delays. The contract and applicable law govern whether an EOT or costs are recoverable.

What are prolongation costs?

Potential time-related costs include site supervision, temporary facilities, equipment hire, extended administration and other substantiated expenditure. An EOT does not automatically entitle the contractor to recover them. The contractor must prove a separate legal or contractual basis and causal loss.

Delay versus disruption

Delay concerns the impact on completion; disruption concerns productivity loss or inefficient working. A project may suffer disruption without an extension to the completion date. The evidence and valuation may differ.

6. UAE law, liquidated damages and dispute resolution

Which Civil Transactions Law applies?

The UAE's Federal Decree-Law No. 25 of 2025 came into force on 1 June 2026, replacing the former Federal Law No. 5 of 1985. The governing statutory provisions, commencement date and transitional position must be assessed for each contract and dispute. Do not cite old Civil Code article numbers as current law without verifying the applicable regime.

Can an employer still claim delay damages?

Potentially, for contractor-responsible delay outside a valid EOT. Agreed damages and any judicial adjustment must be assessed under the governing contract and applicable law. Neither an EOT request nor an agreed damages clause automatically resolves the issue.

What if the Engineer rejects the claim?

Review the reasons, the applicable determination procedure, further evidence and deadlines for escalation. A FIDIC contract may provide multi-stage dispute mechanisms, potentially including a dispute board, amicable settlement and arbitration. Other contracts may require court proceedings. The dispute forum depends on the executed agreement and jurisdiction.

7. EOT claim checklist

  • Confirm FIDIC edition and all Particular Conditions.
  • Identify qualifying events and risk allocation.
  • Issue notice within the actual contractual deadline.
  • Preserve evidence of notice service.
  • Maintain baseline and updated programmes.
  • Keep site diaries, instructions and correspondence.
  • Demonstrate critical path impact and causation.
  • Assess overlapping employer and contractor delays.
  • Quantify EOT days with a defensible method.
  • Calculate prolongation costs separately.
  • Record mitigation efforts and decisions.
  • Check claim and dispute escalation deadlines.

8. How MGA can assist

Mohamed Ghanem & Associates (MGA) advises developers, contractors and other project participants on construction contracts, EOT notices, delay claims, liquidated damages, prolongation disputes and arbitration or litigation strategy. For a project-specific review of your contract and delay evidence, contact MGA.

9. Frequently asked questions

Is an EOT automatic if the employer causes delay?

No. Contractual entitlement and causation must still be established.

Is 28 days a UAE statutory notice period?

No. It is a common contractual period in certain standard FIDIC claims provisions.

Can a late notice invalidate a claim?

It may affect entitlement; the consequences depend on the actual contract and governing law.

Does every delay to an activity delay completion?

No. A non-critical activity may have float.

What is the best delay analysis method?

There is no universally best method; choose one appropriate to the contract, records and dispute.

Does concurrent delay always defeat an EOT?

No. The legal and technical outcome depends on causation and risk allocation.

Does an EOT include compensation?

No. Prolongation costs require a separate basis and proof.

Can weather justify an EOT?

Potentially, if the contractual conditions and completion impact are proved.

Can a subcontractor claim an EOT?

Potentially, under the subcontract's own terms.

Can the employer impose liquidated damages after an EOT?

Potentially, for uncompensated contractor-responsible delay, subject to applicable law.

Are the 1999 and 2017 FIDIC procedures identical?

No. Their claims procedures differ and may be amended.

Is the SCL Protocol binding in the UAE?

Not by itself. It is professional guidance, not legislation.

Can an EOT dispute go to arbitration?

Yes, where a valid arbitration agreement applies.

What records matter most?

The executed contract, notices, updated programmes, contemporaneous site records and a sound causal analysis.

Official sources and legal review