Off-Plan Project Cancellation and Investor Remedies in Abu Dhabi

Mr. Mohamed Ghanem

Published

Updated

Off-Plan Project Cancellation and Investor Remedies in Abu Dhabi

Purchasing an off-plan property in Abu Dhabi provides investors with an opportunity to acquire real estate before construction is completed. However, when a developer fails to commence construction, abandons a development or becomes unable to complete a project, purchasers may face considerable financial and legal uncertainty.

For investors who have already paid substantial purchase instalments, the primary concern is often whether they can recover their investment and which legal procedures are available.

When an off-plan property project is cancelled in Abu Dhabi, affected purchasers may have statutory and contractual rights to recover funds. However, the amount recoverable and the applicable procedure depend on the project's official status, available escrow funds, contractual obligations and the circumstances leading to cancellation.

Abu Dhabi has a distinct real estate regulatory framework that establishes mechanisms for investigating stalled developments, protecting purchaser funds, facilitating alternative project completion and distributing remaining escrow balances.

Understanding these mechanisms is essential before pursuing repayment, contractual termination or compensation.

1. Understanding Off-Plan Project Cancellation in Abu Dhabi

1.1 What Is an Off-Plan Property Project?

An off-plan property is a real estate unit purchased before the completion of its construction.

The purchaser typically enters into a Sale and Purchase Agreement (SPA) with the developer and makes payments according to an agreed payment schedule.

These payments may be linked to:

  • Reservation of the property.
  • Execution of the purchase agreement.
  • Construction milestones.
  • Specified contractual payment dates.
  • Completion and handover requirements.

The transaction remains subject to applicable property registration, development approval and escrow account requirements.

1.2 What Constitutes Project Cancellation?

Project cancellation involves the discontinuation of a real estate development under circumstances recognised by the applicable regulatory and legal framework.

A development may become a candidate for cancellation where:

  • The developer fails to commence construction without an acceptable justification.
  • Construction activities have been abandoned.
  • The developer becomes unable to complete the development.
  • Financial or regulatory complications prevent completion.
  • The competent authority determines that the development cannot proceed.

However, a construction suspension, delayed handover or developer announcement does not necessarily establish that a project has been legally cancelled.

Purchasers should obtain reliable confirmation of the development's official status before determining their legal options.

1.3 Project Cancellation Versus Individual Contract Termination

One of the most important distinctions in Abu Dhabi property law is the difference between cancellation of an entire development and termination of an individual purchaser's agreement.

CircumstanceLegal significancePotential remedy
Construction delayThe project remains active but completion is delayedPerformance, regulatory intervention or qualifying compensation
Developer abandons constructionPotential failure to complete the developmentInvestigation, alternative completion or repayment procedures
Entire project is officially cancelledDevelopment-level cancellationStatutory escrow distribution and potential additional recovery
Purchaser defaults on instalmentsIndividual contractual non-performanceApplicable notice, termination, resale and refund procedures
Purchaser seeks contractual terminationIndividual contractual disputeNegotiated or legally determined termination
Developer agrees to repay the purchaserPotential contractual repayment obligationSettlement enforcement or repayment claim

Cancellation of an individual property unit does not necessarily mean that the entire development has been cancelled.

The distinction directly affects the applicable law, refund calculations and available legal remedies.

2. Legal Framework Governing Project Cancellation in Abu Dhabi

2.1 Abu Dhabi Law No. 3 of 2015

The principal legislation governing the real estate sector is Abu Dhabi Law No. 3 of 2015 concerning the Regulation of the Real Estate Sector, as subsequently amended.

The legislation establishes requirements concerning real estate development activities, off-plan sales, project escrow accounts, developer obligations and investor protections.

Particularly relevant provisions include:

  • Article 20: Protection of project escrow funds against attachment, subject to qualifying claims.
  • Article 22: Depositor access to relevant escrow account statements.
  • Article 25: Regulatory intervention concerning failure to commence or deliver a development.
  • Article 26: Measures for protecting depositors where a developer fails to complete a project.

These provisions form an important part of Abu Dhabi's statutory framework for distressed and cancelled real estate developments.

2.2 Administrative Decision No. 250 of 2015

Abu Dhabi Administrative Decision No. 250 of 2015 concerning Project Escrow Accounts provides implementing procedures relevant to distressed real estate developments.

Its provisions address regulatory complaints, investigations, challenges to cancellation decisions and applications for repayment from project escrow accounts.

The decision should be read alongside the governing legislation and subsequent amendments.

2.3 Law No. 2 of 2025 and Subsequent Regulatory Developments

Abu Dhabi's real estate regulatory framework has continued to develop following the amendment of Law No. 3 of 2015 by Law No. 2 of 2025.

On 27 March 2026, the Abu Dhabi Media Office published an official announcement concerning new real estate regulatory decisions issued by the Department of Municipalities and Transport.

These developments include:

  • Administrative Decision No. 24 of 2025, concerning controlled disbursements from project escrow accounts before the conventional 20% completion threshold.
  • Administrative Decision No. 165 of 2025, concerning developer compensation and refunds following cancellation and resale of individual units where purchasers breach their contractual obligations.

The relevant decisions are available through the ADREC official real estate rules and regulations collection.

Purchasers should not rely exclusively on the original 2015 legislation when assessing a contemporary property dispute. Applicable amendments and implementing decisions must also be examined.

2.4 The Role of Abu Dhabi Government Authorities

The Abu Dhabi Real Estate Centre (ADREC) and the Department of Municipalities and Transport (DMT) are important institutions within Abu Dhabi's real estate regulatory framework.

Their respective functions may involve:

  • Real estate development regulation.
  • Project registration and monitoring.
  • Escrow account supervision.
  • Regulatory investigations.
  • Developer compliance.
  • Property purchaser protection.
  • Specialised dispute settlement mechanisms.

The older legislation refers to authorities under their institutional names at the time of enactment. Purchasers should confirm which current authority exercises the relevant function.

2.5 Properties Within Abu Dhabi Global Market

The Abu Dhabi Global Market (ADGM) operates a distinct legal and real estate regulatory framework.

Investors acquiring properties within ADGM, including its jurisdiction over Al Reem Island, should investigate the applicable real property and off-plan development regulations separately.

The procedures discussed in this article principally concern the ordinary Abu Dhabi real estate framework outside ADGM.

3. When Can an Off-Plan Development Be Cancelled?

3.1 Failure to Commence Construction

Article 25(1) of Abu Dhabi Law No. 3 of 2015 provides a mechanism for regulatory investigation where a developer has failed to commence a development in accordance with its contractual commitments.

The mechanism applies where purchasers representing at least 5% of the real estate units sold submit a qualifying complaint to the competent authority.

An investigation may then determine whether the developer has unjustifiably failed to commence the project.

Where the statutory conditions are established, the authority may cancel the development and initiate the applicable escrow distribution procedures.

The 5% threshold relates to this particular collective complaint and investigation mechanism. It should not be interpreted as preventing an individual purchaser from investigating other contractual, regulatory or judicial remedies.

For example, if 200 units have been sold in a qualifying development, the threshold would correspond to purchasers representing at least 10 sold units.

Meeting that threshold does not, by itself, compel the regulator to cancel the project.

3.2 Failure to Complete a Development

Construction may have commenced before the developer encounters financial, operational or regulatory difficulties that prevent completion.

Article 26 of Abu Dhabi Law No. 3 of 2015 establishes a mechanism for protecting depositors where the developer fails to complete a project.

Importantly, the legislation does not immediately treat repayment as the only possible solution.

The escrow account trustee may take approved protective measures intended to secure project completion.

These measures may involve:

  • Financial restructuring.
  • Arrangements involving the project's financier.
  • Completion by another developer.
  • Other measures approved by the competent authority.

The continuation of a distressed development may be considered before the distribution of remaining escrow funds.

For some investors, obtaining the contracted property may provide a more commercially beneficial outcome than receiving a partial refund.

3.3 The Six-Month Completion Solution Period

Article 26 establishes a six-month period, calculated from the relevant regulatory approval of protective measures, during which a solution for completing the development may be pursued.

If completion remains impossible within that statutory framework, the legislation provides for supervised distribution of the remaining project escrow balance.

Investors should distinguish this period from:

  • Six months after signing the SPA.
  • Six months after the original contractual handover date.
  • Six months after construction stops.
  • Six months after an investor submits a complaint.

The statutory completion solution period is not a universal six-month refund guarantee.

3.4 Prolonged Handover Delays

Article 25 also addresses developer delays in delivering a real estate development.

Where delivery exceeds the relevant regulatory completion schedule by more than six months, the competent authority may impose a delay penalty benefiting affected purchasers, subject to statutory conditions.

The developer may establish that the delay arose from circumstances outside its control.

Article 25 also contains a transitional exclusion for certain older developments that had already achieved at least 50% completion when the legislation became applicable.

A delayed purchaser should therefore investigate the applicable contractual completion date, the regulatory schedule and the statutory exceptions before assuming that a penalty or cancellation entitlement exists.

A six-month delivery delay does not automatically terminate an off-plan purchase agreement.

4. Escrow Account Protection and Distribution of Investor Funds

4.1 What Is a Project Escrow Account?

A project escrow account is a regulated account associated with a particular real estate development.

It is used to receive and administer qualifying purchaser payments and project financing funds.

The escrow framework is designed to provide oversight over the use of project-related funds and reduce the risk of their unrestricted use for unrelated purposes.

For purchasers, an important preliminary consideration is whether their payments were deposited and properly recorded in the relevant project account.

4.2 Protection Against Attachment

Article 20 of Abu Dhabi Law No. 3 of 2015 establishes restrictions on attachment of money held within a project's escrow account.

It also preserves specified claim rights of purchasers, contractors and project financiers in qualifying circumstances involving project abandonment, cancellation, recognised suspension, cancellation of the developer's registration or a final judicial decision.

This distinction is significant because the project escrow account is subject to statutory protections and procedures that may differ from those applicable to a developer's ordinary corporate bank accounts.

A purchaser cannot necessarily obtain unrestricted access to the escrow balance simply by establishing an outstanding contractual claim.

4.3 Access to Escrow Account Statements

Under Article 22, qualifying depositors may access relevant statements maintained by the account trustee and obtain copies.

These documents may assist purchasers in establishing:

  • The amount recorded against their transaction.
  • Whether the developer deposited the relevant payments.
  • Discrepancies between payment receipts and official accounting records.

The scope of an individual purchaser's access should be assessed under the applicable rules.

4.4 Updated Rules Concerning the 20% Completion Threshold

Historically, Abu Dhabi's real estate escrow framework restricted disbursement before a specified construction completion threshold.

However, Administrative Decision No. 24 of 2025 introduced a regulatory mechanism addressing controlled withdrawals before 20% project completion.

Purchasers should therefore avoid assuming that every early-stage withdrawal necessarily constitutes unlawful conduct.

The relevant approvals, regulatory controls and circumstances of the disbursement must be examined.

4.5 How Are Remaining Escrow Funds Distributed?

Where the statutory conditions for distribution are satisfied, Article 26(2) establishes an order of priority for the remaining project balance.

PriorityRecipient category
FirstOutstanding approved account administration expenses
SecondProject financiers, property purchasers and their financiers, proportionately where necessary
ThirdProject contractors and suppliers, proportionately if the remaining balance is insufficient
FourthThe developer, from any applicable remaining balance

The distribution takes place under regulatory supervision.

This means purchasers may share a distribution category with qualifying financiers rather than receiving unconditional priority over all other parties.

The Escrow balance available at cancellation may be insufficient to return every purchaser's complete investment.

4.6 Can Investors Recover an Escrow Shortfall?

Yes, potentially.

Article 26(3) preserves contractual recourse against the developer for amounts remaining outstanding after the statutory distribution.

This is an important protection for purchasers whose allocated escrow repayment is less than their legally recoverable entitlement.

However, pursuing the shortfall may require additional contractual or judicial procedures.

5. Investor Refund Rights and Other Legal Remedies

5.1 Applying for an Escrow Refund

Article 13 of Administrative Decision No. 250 of 2015 establishes a procedure for qualifying off-plan purchasers to request their share of project escrow funds following a cancellation decision.

The required application documentation includes:

  • The off-plan sale agreement.
  • Relevant correspondence with the developer.
  • A record of purchaser payments.
  • Confirmation from the escrow custodian of funds attributed to the transaction.
  • Evidence of payment of applicable administrative fees.

Additional documentation may be required depending on the case.

Following assessment, the competent authority may determine the amount payable through the project account.

An investor should first confirm that the cancellation and the transaction satisfy the requirements of this procedure.

5.2 Full Refund Versus Partial Escrow Recovery

Article 11 of Administrative Decision No. 250 of 2015 addresses the developer's repayment obligations in qualifying cases of cancellation arising from unjustified failure to commence construction.

However, the developer's legal repayment obligation and the amount immediately available through the escrow distribution procedure are different matters.

For example, a purchaser may establish an entitlement to recover the full purchase payments while only a proportion of those funds remains available through the project account.

The outstanding amount may require a separate recovery claim.

A partial escrow repayment does not necessarily extinguish an investor's entitlement to pursue the remaining amount.

Before accepting any repayment, purchasers should examine whether accompanying documentation includes a settlement or release of further claims.

5.3 Contractual Repayment and Termination Claims

Where the development has not been officially cancelled, an investor may still have grounds to investigate contractual remedies arising from developer non-performance.

These may include:

  • Performance of outstanding obligations.
  • Legally effective termination of the agreement.
  • Repayment or restitution.
  • Compensation for qualifying losses.
  • Enforcement of an existing settlement agreement.

The applicable UAE civil legislation, including its temporal application to the relevant transaction, must be considered.

A purchaser should not assume that an informal statement of cancellation or a unilateral demand for repayment automatically establishes a legally enforceable termination.

5.4 Compensation for Financial Loss

An investor may experience financial losses beyond the purchase payments themselves.

These could involve financing costs, additional expenditure or other losses allegedly resulting from the developer's failure to perform.

Whether such amounts are recoverable depends on the applicable legislation, contractual provisions, supporting evidence and the relationship between the breach and the claimed loss.

Purchasers should distinguish between:

  • Return of purchase payments.
  • Contractually agreed compensation.
  • Compensation for proven additional losses.
  • Speculative investment returns.
  • Regulatory delay penalties.

The cancellation of a development does not automatically establish entitlement to every category of financial loss.

5.5 Individual Unit Cancellation Following Purchaser Default

Administrative Decision No. 165 of 2025 addresses a separate situation involving termination of individual off-plan sale agreements following purchaser default, with subsequent cancellation and resale of the relevant unit.

The applicable compensation and refund calculation may depend on construction progress, contractual terms and the relevant regulatory determination.

These rules should not be used to calculate refunds arising from cancellation of an entire real estate development.

Similarly, purchasers should not assume that stopping their instalments automatically converts a developer-related dispute into a valid purchaser cancellation claim.

Legal advice should be obtained before suspending contractual payments.

5.6 Developer Insolvency and Financial Recoverability

A developer may experience financial distress without being subject to formal insolvency proceedings.

Where formal insolvency or bankruptcy procedures exist, investors should establish how those procedures affect their claims and the statutory protections applicable to project funds.

Considerations include:

  • The identity of the contracting developer.
  • Available project and corporate assets.
  • Existing security interests.
  • Other creditor claims.
  • Pending enforcement proceedings.
  • The legal treatment of outstanding investor entitlements.

Even where a repayment claim is legally established, financial recovery remains dependent on the available assets and applicable procedures.

6. How to Pursue a Cancelled Property Project Claim in Abu Dhabi

Step 1: Establish the Official Project Status

Obtain reliable confirmation of whether the development is active, suspended, abandoned or officially cancelled.

Where cancellation has occurred, obtain the available decision and establish its scope and notification date.

Step 2: Review the Purchase Agreement and Registration Records

Examine the signed SPA, payment schedule, amendments and initial property registration documentation.

Registration issues may affect the legal assessment of an investor's transaction.

Step 3: Prepare a Complete Payment Reconciliation

Identify every amount paid towards the property, including:

  • Reservation payments.
  • Purchase instalments.
  • Registration charges.
  • Brokerage fees.
  • Financing-related expenditure.

Different categories of payment may require different legal grounds for recovery.

Step 4: Examine the Escrow Account Position

Establish the identity of the escrow trustee and obtain available statements relating to the purchaser's payments.

Compare those statements with the investor's own receipts and bank records.

If funds appear to be missing, investigate the discrepancy before making assumptions about the developer's conduct.

Step 5: Assess the Regulatory Complaint Procedure

Where the developer has failed to commence construction, Article 11 of Administrative Decision No. 250 of 2015 addresses complaint assessment and regulatory investigation.

Purchasers should establish whether the collective complaint mechanism applies and whether other procedures are available.

A properly documented submission should identify the contractual commitments, evidence of non-performance and relevant project information.

Step 6: Preserve Rights of Challenge

Article 11 of Administrative Decision No. 250 of 2015 provides for a regulatory grievance period of 15 days from notification of the relevant decision.

It also provides for a subsequent court challenge within 60 days from notification of the decision on that grievance.

These periods concern the specific decision and challenge process described in that provision.

They are not general limitation periods for all real estate disputes.

Any investor receiving a formal cancellation or grievance decision should promptly establish the applicable challenge procedure and deadline.

Step 7: Consider Specialised Dispute Settlement

The Abu Dhabi Real Estate Dispute Settlement Centre (Taswea) provides a specialised mechanism for consensual resolution of qualifying real estate disputes.

Depending on the matter, the process may involve referral through the Abu Dhabi Judicial Department and settlement discussions.

Where a dispute cannot be resolved consensually, proceedings before the competent court may be necessary.

The centre's competence must be established before assuming that it handles every cancelled development or escrow distribution dispute.

Step 8: Assess Judicial Recovery and Enforcement

Where administrative repayment or settlement does not resolve the investor's financial entitlement, further proceedings may be required.

The appropriate legal route may depend on:

  • The nature of the project and cancellation decision.
  • The legal basis of the outstanding claim.
  • Contractual dispute resolution arrangements.
  • The competent court or arbitral tribunal.
  • Existing insolvency proceedings.
  • Applicable enforcement restrictions.

An enforceable decision does not, by itself, establish that sufficient assets exist to satisfy the amount awarded.

Illustrative Example: Partial Recovery Following Project Cancellation

Assume that an investor paid AED 800,000 towards an off-plan apartment in Abu Dhabi.

The developer becomes unable to complete the development, and the applicable regulatory investigation ultimately leads to cancellation and distribution of the remaining project escrow funds.

Following the statutory assessment, the investor receives AED 300,000 through the distribution process.

The remaining AED 500,000 is a potential outstanding balance rather than an automatically enforceable award.

In this hypothetical scenario, the investor should investigate:

  1. Whether the distribution amount was calculated correctly.
  2. The developer's outstanding repayment obligations.
  3. Whether any settlement or release has been signed.
  4. The appropriate legal basis for pursuing the shortfall.
  5. The developer's financial position and available assets.
  6. The cost and practical prospects of further recovery proceedings.

The hypothetical escrow repayment does not automatically determine the investor's complete legal entitlement.

The remaining claim must be assessed independently.

7. Protecting Your Investment and Obtaining Legal Assistance

Practical Checklist for Affected Property Investors

Project and developer verification

  • Establish the developer's registered legal identity.
  • Verify the development's official status.
  • Obtain available cancellation or suspension decisions.
  • Investigate whether alternative completion arrangements exist.
  • Identify the competent regulatory authority.

Contractual and registration documentation

  • Obtain the complete signed SPA.
  • Review all contractual amendments.
  • Obtain initial property registration records.
  • Review termination and repayment provisions.
  • Identify applicable contractual notice requirements.

Payment and escrow verification

  • Compile all payment receipts and bank transfers.
  • Prepare a complete payment reconciliation.
  • Obtain available escrow payment statements.
  • Investigate discrepancies between payment records.
  • Obtain details of any proposed escrow distribution.
  • Calculate the potentially outstanding balance.

Legal recovery assessment

  • Establish whether the statutory complaint mechanism applies.
  • Review regulatory notification and challenge deadlines.
  • Investigate available contractual repayment remedies.
  • Assess proposed settlement terms before signing.
  • Identify the appropriate dispute resolution forum.
  • Assess developer solvency and financial recoverability.
  • Preserve evidence of additional financial losses.

How Mohamed Ghanem & Associates Can Assist

Off-plan project cancellation can involve complex interactions between property regulation, contractual rights, escrow arrangements, developer obligations and financial recovery procedures.

Through its Distress & Canceled Projects legal services, Mohamed Ghanem & Associates assists property investors in assessing legal issues arising from distressed, abandoned and cancelled developments.

The firm's distressed property and developer dispute services in Abu Dhabi may assist investors with:

  • Reviewing off-plan property agreements.
  • Assessing project cancellation and developer default.
  • Examining statutory investor protections.
  • Reviewing escrow account repayment issues.
  • Assessing potential outstanding financial entitlements.
  • Advising on regulatory investigations and challenges.
  • Reviewing proposed repayment and settlement arrangements.
  • Evaluating litigation and enforcement options.

The firm's broader Real Estate Expertise legal services may also be relevant where the dispute involves contractual obligations, property registration and competing real estate rights.

Investors considering contractual termination may additionally benefit from a review under the firm's Contract Termination legal services.

Has your off-plan property development in Abu Dhabi been suspended, abandoned or officially cancelled?

Contact Mohamed Ghanem & Associates to arrange a legal consultation and obtain an assessment of your contractual rights, potential repayment entitlement and available legal recovery options.

8. Frequently Asked Questions

1. What happens when an off-plan property project is cancelled in Abu Dhabi?

The applicable legislation establishes mechanisms for protecting investors, investigating alternative completion options and distributing remaining project escrow funds where the necessary conditions are satisfied.

2. Can I obtain a full refund if my Abu Dhabi property project is cancelled?

Potentially. The investor's legal entitlement depends on the cancellation circumstances and applicable legislation. Actual recovery may also depend on available escrow balances and other developer assets.

3. Which authority regulates off-plan project cancellation in Abu Dhabi?

The Department of Municipalities and Transport and Abu Dhabi Real Estate Centre form part of the relevant regulatory framework. The competent authority and applicable procedure should be established for the individual development.

4. What is the 5% purchaser complaint requirement?

Article 25 of Abu Dhabi Law No. 3 of 2015 establishes a particular investigation mechanism where purchasers representing at least 5% of sold units submit a qualifying complaint concerning failure to commence construction.

5. Can an individual purchaser pursue a claim without meeting the 5% threshold?

Potentially. The threshold concerns the specific collective investigation mechanism. Other contractual, regulatory or judicial remedies may remain available to individual purchasers.

6. Does a six-month construction delay automatically cancel my SPA?

No. Abu Dhabi legislation contains different six-month provisions concerning completion solutions and qualifying delivery delays. Neither establishes a universal automatic cancellation right.

7. Can another developer take over a distressed project?

Yes, potentially. Article 26 recognises protective measures aimed at completing developments, which may involve another developer or the project's financier.

8. Are property escrow accounts guaranteed to contain all my payments?

No. Funds may have been lawfully disbursed towards development activities. The purchaser should investigate payment records and the amount available under the applicable escrow framework.

9. How are project escrow funds distributed after cancellation?

The legislation establishes a defined order of distribution involving account administration expenses, purchasers, financiers, contractors, suppliers and the developer.

10. Can I recover the difference if my escrow refund is insufficient?

Potentially. Article 26 preserves contractual claims against the developer for qualifying outstanding amounts after escrow distribution.

11. What documents do I need to apply for an escrow refund?

Relevant documents generally include the signed off-plan agreement, developer correspondence, payment evidence and confirmation from the escrow custodian, together with the other requirements of the applicable procedure.

12. Can I claim compensation in addition to a refund?

Potentially, where there is an applicable legal basis and sufficient evidence of recoverable additional losses. Compensation is not automatically awarded whenever a development is cancelled.

13. Can I challenge a project cancellation decision?

The implementing regulations provide specified grievance and court challenge procedures. The applicable notification date, legal conditions and procedural deadlines should be reviewed promptly.

14. Does Administrative Decision No. 165 of 2025 apply to every cancelled development?

No. It concerns the distinct mechanism involving cancellation and resale of individual off-plan units following purchaser default. Its refund calculations should not automatically be applied to entire project cancellations.

15. Can Taswea help resolve an off-plan property dispute?

Potentially, where the dispute falls within its competence. Taswea facilitates settlement of qualifying real estate disputes but should not be confused with the authority responsible for project cancellation and escrow distribution.

16. When should I consult a property dispute lawyer in Abu Dhabi?

Legal advice should be considered when construction has been abandoned, a cancellation decision is issued, escrow repayments appear insufficient or the investor needs to assess termination, compensation or further financial recovery options.


This article provides general legal information concerning off-plan project cancellation and investor remedies in Abu Dhabi. It does not constitute individual legal advice. Applicable legislation, regulatory procedures, repayment entitlements and financial recovery depend on the specific circumstances and jurisdiction of each development.